Industrial & Residential Land Development
Saskatchewan Industrial Park

Saskatchewan Industrial Park consists of the construction of 11 fully serviced rural industrial lots. The construction includes the installation of watermain, a portion of sanitary sewer main, site grading with ditches and roadways designed with a rural cross section. A rural cross section utilizes site grading and ditches to manage storm water rather than a storm pipe system. This subdivision is the first within City limits to be designed as a rural cross section.

This project was constructed in two parts:
  • Part one consisted of site grading and ditches as well as the installation of all deep services. This was completed early summer 2012. 
  • Part two consisted of constructing the surface works including landscape and the construction of the roadways. This work is mostly complete with one section of roadway over utility crossings to be completed as well as some deficiency repairs.


Hill Industrial Park Phase 2 Stage 3

Hill Industrial Phase 2 Stage 3 consists of installing watermain, sanitary sewer main, storm sewer main, and constructing roadways to service five industrial lots including the new City of Lloydminster Operations Centre property.

Hill Industrial Phase 2 Stage 3 includes the following section:

  • 52 Street from 63 Avenue to 67 Avenue 
  • 67 Avenue from 52 Street to 56 Street. 

To date, all underground work has been completed on 52 Street and 67 Avenue. The surface work is mostly complete with one section of roadway over a utility crossing to be completed as well as some deficiency repairs.


Hill Industrial Park Phase 7 Stage 2

In 2013, the work in Hill Industrial Phase 7 Stage 2 consisted of providing service connections to land in the northwest corner of the development. The construction included the installation of water main, sewer main, storm sewer main, site grading, and ditch work. This work was completed in 2013. In 2014, the roadwork in the areas that were serviced in 2013 will be completed. The servicing and roadway construction of 62 Street will also be completed, connecting it to 75 Avenue.


Parkview Estates Phase 6 Stage 1

Parkview Estates Phase 6 Stage 1 consists of installing watermain, sanitary sewer main, storm sewer main, landscaping and constructing roadways to service 104 residential lots and two multi-family/commercial lots adjacent to 75 Avenue and 34 Street. This project was constructed in two parts:

  • Part one consisted of site grading and the installation of all deep services, and was completed in 2013.
  • Part two consisted of constructing the surface works including landscape and the construction of the roadways. This began in 2013 and is nearly complete with some deficiency repairs and roundabout construction remaining. 

Shallow utilities including gas, power, and communications were installed over the winter with some clean-up work required in the spring of 2014. Once this is complete, fencing will be installed.


Parkview Estates Phase 6 Stage 2

Parkview Estates Phase 6 Stage 2 consists of installing watermain, sanitary sewer main, storm sewer main, landscaping and constructing roadways to service 62 residential lots adjacent to 70 Avenue and 35 Street.

This project will be constructed in two parts. Part one consisted of site grading and the installation of all deep services. The construction of part one was completed in 2013. Part two will consist of constructing the surface works including landscape and the construction of the roadways, and will begin in the spring of 2014. The completion date for surface works is projected to be late summer of 2014.


Colonial Park East Phase 2

Colonial Park East Phase 2 consists of installing watermain, sanitary sewer main, storm sewer main, landscaping and constructing roadways to service 55 residential lots and two multi-family/commercial lots adjacent to 40 Avenue and 31 Street.

This project will be constructed in two parts. Part one consisted of site grading and the installation of all deep services. The construction of part one was completed in 2013. Part two will consist of constructing the surface works including landscape and the construction of the roadways, which will begin in the spring of 2014. The completion date for surface works is projected to be late summer of 2014.


Wigfield Industrial Phase 1 Stage 2 - 41 Street Extension

Wigfield Industrial Phase 1 Stage 2 – 41 Street Extension consists of the construction of roadway connecting 41 Street west to 40 Avenue. The construction includes the installation of water main, sanitary sewer main, services to a single industrial lot, roadways and ditches.

The installation of the mains and services was completed in 2012. The roadwork was started in the summer of 2013 and is expected to be complete in the spring of 2014.