Search

44 Street: Phase 2 nearing completion as crews prepare for paving
Posted on Thursday, October 21, 2021 02:28 PM
Lloydminster, AB/SK – The second phase of the concrete intersection at Highway 16 (44 Street) and 62 Avenue is complete, allowing crews to focus on paving the highway between 62...

Road closure: 75 Ave between Highway 16 and 62 Street
Posted on Tuesday, October 12, 2021 10:22 AM
Lloydminster, AB/SK – Motorists and road users are advised that Canadian National Railway Company (CN Railway) will conduct rehabilitative work to the railway crossing at 75 Avenue,...

44 Street: Highway 16 concrete block placement, 62 Ave north open for traffic
Posted on Friday, September 24, 2021 10:20 AM
Lloydminster, AB/SK – Favourable weather the past few weeks has helped increase production and maximize site presence.
Major activity over the next week will include the placement...

44 Street: East, westbound traffic to flip before September 7 morning commute
Posted on Monday, September 06, 2021 06:00 PM
Lloydminster, AB/SK – East and westbound traffic along Highway 16 (44 Street) is scheduled to flip from the south to the north side of the highway before motorists drive to work...

44 Street: Phase 1 nearing completion, traffic flow to flip
Posted on Wednesday, September 01, 2021 04:13 PM
Lloydminster, AB/SK – East and westbound traffic along Highway 16 (44 Street) from 59 Avenue through 75 Avenue is scheduled to flip from the south side of the highway to the...

Road closure: 49 Ave between 52 St and 53 St
Posted on Monday, August 23, 2021 02:13 PM
In conjunction with Impact Construction Inc., the City of Lloydminster will connect underground water and sewer lines on the 4800 block of 49 Avenue, beginning Tuesday, August...

44 Street: Phase 1 completion date delayed, crews to complete other areas of project
Posted on Wednesday, August 18, 2021 04:21 PM
Unforeseen circumstances surrounding the final paving of Phase I have delayed transitioning traffic to the north side of Highway 16 (44 Street) to the week of August 23, 2021.
In...

44 Street: East, westbound traffic on track to flip week of August 16
Posted on Monday, August 09, 2021 03:57 PM
Lloydminster, AB/SK – With the placement of the asphalt concrete pavement along Highway 16 between 62 Avenue and 75 Avenue well underway, Phase I of the rehabilitation project...

Impending lane restriction, eastbound 52 Street
Posted on Friday, August 06, 2021 03:19 PM
Lloydminster, AB/SK – The City of Lloydminster, in conjunction with Rusway Construction Ltd., will repair an underground valve in the area of the 5300 block of 52 Street...

44 Street: Phase 1 nearing completion
Posted on Thursday, July 29, 2021 09:20 AM
Lloydminster, AB/SK – Traffic along Highway 16 (44 Street) will soon switch to the north side of the highway as the first phase of the rehabilitation project nears completion.
The...