Phase I of the project consists of the rehabilitation of the north side of Highway 16 (44 Street). Upon completion of the north side of the highway, the construction zone and signage will alternate, and Phase II of the project will be initiated. Phase II of the project consists of the rehabilitation of the south side of 44 Street, and is anticipated to start July/August 2021.
The construction limits for the entire project will be along Highway 16 (44 Street) between west of 59 Avenue and 75 Avenue.
Intersection of Highway 16 (44 Street) and 62 Avenue
- Concrete intersection
- Water main replacement – complete replacement
- Sanitary main replacement – complete replacement
- Storm main – replacement is not required due to current age and condition
Highway 16 (44 Street) between 62 Avenue and 75 Avenue
- 62 Avenue to 66 Avenue
- Complete rehabilitation of the roadway while minimizing concrete curb and gutter replacements
- 66 Avenue to 70 Avenue
- Asphalt milling, inlay and final overlay
- 70 Avenue to 75 Avenue
- Asphalt milling and overlay