As reconstruction work continues on 49 Avenue and 50 Street, the intersection remains closed to all traffic, and 50 Street east of 50 Avenue is closed to motor vehicles and pedestrians. For business access, please use the appropriate alley.
What's Happening This Week (May 29 to June 2, 2023)
- Continue the installation of the storm, sanitary and water mains west of 49 Avenue along 50 Street.
- Continue underground utility installation at the intersectionof 49 Avenue and 50 Street. Once complete, aboveground repairs will begin.
Tasks Completed the Week of May 23-27, 2023:
- Crews began working on underground infrastructure west of 49 Avenue along 50 Street after completing underground utility connections and installations at 50 Street and 49 Avenue.
- Completed the tie-in into the storm manhole at the 49 Avenue and 50 Street intersection.
- Concrete removal and asphalt millings in alley
Weather permitting, Phase 1 is from May 15, 2023, to June 4, 2023.
To help ensure the safety of workers, motorists and pedestrians, the City of Lloydminster reminds everyone to allow extra time for travel, obey all signage and follow proper detours. Pedestrians should take extra precautions and maintain a safe distance from construction fencing and equipment.
The project’s second phase begins at the conclusion of Phase 1 and is expected to be completed in early October, weather permitting.
Downtown Parking & Navigation
During construction, 24 temporary parking stalls will be available at Synergy Credit Union at the corner of 49 Avenue and 49 Street. These temporary parking stalls will replace the 20 spots that will be unavailable during construction. Motorists are advised to use the dedicated parking stalls.
Detour and local traffic only signs will be placed throughout the area to show traffic and visitors how to access properties while avoiding the construction site. There will be no parking or pedestrian access permitted in the work zone until the end of the construction period. Emergency access will be maintained to all affected businesses at all times through alternate routes.
Project Scope
The program consists of replacing and upgrading underground municipal infrastructure throughout the downtown core to maintain the serviceability and longevity of the city’s underground systems. Further work includes removing and reconstructing the roadway surface, sidewalks, benches and other public amenities to bring the DARP's vision to life.
During construction, access to properties along 50 Street will be restricted, and portions of existing sidewalks will be left In place to permit access to business front doors. Back alleys will remain open at all times for business owners, employees and customers.
Work will take place between 6 a.m. and 10 p.m. Monday through Saturday and between 7 a.m. and 8 p.m. on Sundays.
Learn More
Visit Lloydminster.ca/CBDRP to learn more about the central business district replacement program. This web page includes traffic accommodations and will host regular project updates.
More information about the City of Lloydminster’s 2023 engineering capital infrastructure projects is available at Lloydminster.ca/engineering.
Traffic updates are available at Lloydminster.ca/traffic.